David Krutko

Mackenzie Delta

Statements in Debates

Debates of , 16th Assembly, 2nd Session (day 41)

Thank you, Mr. Bromley. We’re on page 3-4, Municipal and Community Affairs, Regional Operations, Infrastructure Investment Summary, Total Infrastructure Investment Summary: $28.09 million.

Department of Municipal and Community Affairs, Activity Summary, Regional Operations, Infrastructure Investment Summary, Total Infrastructure Investment Summary: $28.09 million, approved.

Debates of , 16th Assembly, 2nd Session (day 41)

In regard to the urgency of this project and the timelines that we’re looking at, I’d just like to ask the Minister: where does the priority of capital projects fit by way of urgency in regard to other types of capital projects? I’ll use as an example water treatment facilities for communities. For me that’s an urgent capital project. Most of these projects will not see the light of day until 2010, yet they were approved in previous years. I find it kind of interesting that this project happened to be fast tracked, moved to the front of the line, and is going to be constructed prior to...

Debates of , 16th Assembly, 2nd Session (day 41)

We can go back to page 2-2 in regard to Department Summary, Infrastructure Investment Summary, Total Infrastructure Investment Summary: $5.152 million.

Financial Management Board Secretariat, Department Summary, Infrastructure Investment Summary, Total Infrastructure Investment Summary: $5.152 million, approved.

Debates of , 16th Assembly, 2nd Session (day 41)

Mr. Speaker, your committee has been considering Tabled Document 93-16(2), Northwest Territories Capital Estimates 2009–2010, and would like to report progress with one motion being adopted.

Mr. Speaker, I move that the report of Committee of the Whole be concurred with.

Debates of , 16th Assembly, 2nd Session (day 41)

That answer was really helpful. I would like to ask Mr. Aumond to elaborate a little more on exactly what the $500,000 is going to be spent for.

Debates of , 16th Assembly, 2nd Session (day 41)

Mr. Chairman, just restating that. Basically, $1.3 million has been expended for 2008–2009, which is this fiscal year. Next fiscal year, 2009–2010, we’re expending $6 million. Then future years, 2010–2011, will come in at $5.7 million. Is that the schedule we’re now on?