Debates of September 27, 2023 (day 162)

Date
September
27
2023
Session
19th Assembly, 2nd Session
Day
162
Members Present
Hon. Diane Archie, Hon. Frederick Blake Jr., Mr. Bonnetrouge, Hon. Paulie Chinna, Ms. Cleveland, Hon. Caroline Cochrane, Mr. Edjericon, Hon. Julie Green, Mr. Jacobson, Mr. Johnson, Ms. Martselos, Ms. Nokleby, Mr. O’Reilly, Ms. Semmler, Hon. R.J. Simpson, Mr. Rocky Simpson, Hon. Shane Thompson, Hon. Caroline Wawzonek, Ms. Weyallon Armstrong
Topics
Statements

Return to Written Question 65-19(2): Public-Private Partnership Projects Capital and Operating Costs and Revenues

Speaker: Mr. Rutland

Thank you, Mr. Speaker. I have a Return to Written Question 6519(2) asked by the Member for Frame Lake on May 25th, 2023, regarding PublicPrivate Partnership Projects Capital and Operating Costs and Revenues.

Over the past ten years the Government of the Northwest Territories has taken part in three. PublicPrivate Partnership, or P3, projects which include the construction of the Mackenzie Valley Fibre Link, the renewal of the Stanton Territorial Hospital and recently the completion of the Tlicho AllSeason Road.

The Mackenzie Valley Fibre Link project involved the construction of a fibre optic line connecting from McGill Lake to the community of Inuvik to extend the delivery of highspeed broadband connectivity to several communities along the Mackenzie Valley. Construction of the project was completed in partnership with Northern Lights General Partnership and was fully operational in June 2017.

A renewal of the Stanton Territorial Hospital was also completed as a P3 project in partnership with Boreal Health Partnership. The project was initiated to address the aging building systems in the former Stanton Hospital building and provide upgraded facilities to ensure that effective services could be provided to residents of the Northwest Territories. Patient services delivered in the newly constructed hospital commenced on May 26, 2019.

The most recent P3 project to be completed is the Tlicho AllSeason Road which opened officially on November 30, 2021. The Government of the Northwest Territories worked with North STAR Infrastructure to extend an allseason road 97 km from Highway No. 3 to the community of Whati. Completion of this project allowed for greater yearround access to Whati which had formerly only been accessible via winter road or air travel.

The Member had requested the original projected capital and operations costs and associated revenues for all P3 projects that have occurred over the past ten years. The projected costs for each project are as follows:

For the Mackenzie Valley Fibre Link the projected capital cost was $91 million and the projected operating cost was $85.6 million over the life of the project agreement, a debt servicing cost, which includes principal and interest costs of $147.8 million and $124.6 million was expected in revenues.

The capital projection for the Stanton Renewal project was $350 million, the projected operating expenditures were $326.4 million and the debt servicing costs were projected at $270.7 million.

In relation to the Tlicho AllSeason Road a total of $215.33 million was projected in capital costs along with $149.6 million projected for operating costs over the life cycle of the project agreement and $152.3 million for debt servicing costs.

The Member also requested the actual expenditure and revenue totals for each of the last ten fiscal years for these projects.

Actual capital expenditures for the Mackenzie Valley Fibre Link over the past ten years were as follows:

$69.142 million in 201516;

$25.894 million in 201617;

$3.28 million in 201718.

Actual operating expenditures for the Mackenzie Valley Fibre Link were:

$1.212 million in 201617;

$2.861 million in 201718;

$3.418 million in 201819;

$3.445 million in 201920;

$3.541 million in 202021;

$3.473 million in 202122; and

$5.172 million in 202223.

The actual debt servicing costs related to the fibre link over the tenyear period were:

$9 million in 201718;

$7.4 million in 201819;

$7.5 million in 201920;

$7.4 million in 202021;

$7.6 million in 202122; and

$7.4 million in 202223.

Revenue generated by the fibre link over the requested period was:

$232 thousand in 201617;

$756 thousand in 201718;

$1.184 million in 201819;

$1.461 million in 201920;

$1.457 million in 202021;

$1.844 million in 202122; and

$2.073 million in 202223.

Capital expenditures occurring over the past ten years related to the Stanton Territorial.

Hospital Renewal project totaled:

$4.153 million in 201415;

$36.632 million in 201516;

$105.393 million in 201617;

$92.556 million in 201718;

$80.331 million in 201819; and

$3.924 million in 201920.

Operating costs over the same time frame for the hospital included:

$2.924 million in 201819;

$6.764 million in 201920;

$7.704 million in 202021;

$9.64 million in 202122; and

$11.512 million in 202223.

Costs related to the servicing of debt for the Stanton Renewal project over the tenyear period were:

$2.9 million in 201819;

$10.3 million in 201920;

$10.4 million in 202021;

$10.325 million in 202122; and

$10.258 million in 202223.

Construction of the Tlicho AllSeason Road resulted in the following capital expenditures:

$7.232 million in 201718;

$24.917 million in 201819;

$45.357 million in 202021;

$41.167 million in 202122; and

$1.604 million in 202223.

Operating costs associated with the road were:

$3.87 million in 202122; and

$5.304 million in 202223.

Additionally debt servicing costs for the road over the past ten years totaled:

$1 million in 202122; and

$6.1 million in 202223.

As a percentage of the Capital and Operational budgets presented in the main estimates and capital estimates during the past ten years costs for these projects represented the following percentages of the budgets. I would like to note that I will be providing the percentage of the capital costs as a total of the overall project budget as some expenditures were recorded in specific fiscal years as a result of substantial completion check points.

Capital costs for the Mackenzie Valley Fibre Link accounted for 139 percent of the original P3 budget largely due to additional capital costs that were agreed upon between the Government of the Northwest Territories and the project partner after the completion of the project and for which a supplementary appropriation was approved in 202223.

Operating and debt servicing costs accounted for the following percentages in each fiscal year:

17.3 percent in 201617;

84.8 percent in 201718;

77.34 percent in 201819;

77.53 percent in 201920;

78.22 percent in 202021;

79.16 percent in 202122; and

96.49 percent in 202223.

Revenue generated by the Mackenzie Valley Fibre Link over the past ten years as a percentage of the allocated budget was:

No revenue budgeted in 201617;

64 percent in 201718;

152 percent in 201819;

122 percent in 201920;

121 percent in 202021;

154 percent in 202122; and

122 percent in 202223.

Capital expenditures on the Stanton Renewal Project accounted for 92 percent of the original budget.

Operating and debt servicing costs accounted for the following percentages in each fiscal year:

32 percent in 201819;

93 percent in 201920;

99 percent in 202021;

109 percent in 202122; and

119 percent in 202223.

The percentage of actual capital expenditures related to the Tlicho AllSeason Road in respect to the budget was 98 percent.

The operating and debt servicing costs accounted for:

271 percent in 202122, this was due to the projected commencement date reflected in the original model; and

81 percent in 202223.

Prior to the decision to enter into any P3 agreement a series of analysis is completed to determine the financial, structural, environmental and legal impacts on the territory and the government with respect to the existing infrastructure and service delivery along with proper consultation with Indigenous governments that may be impacted. There is also a Public-Private Partnership Policy that guides the government's use of P3 agreements to complete large scale projects. While the analytical documents are not publicly available the policy documents are. An offer has also been made to present the audit findings in regards to the Stanton Renewal to standing committee to provide greater understanding of this project. Thank you, Mr. Speaker.