Debates of October 19, 2022 (day 123)

Date
October
19
2022
Session
19th Assembly, 2nd Session
Day
123
Members Present
Hon. Diane Archie, Hon. Frederick Blake Jr., Mr. Bonnetrouge, Hon. Paulie Chinna, Ms. Cleveland, Hon. Caroline Cochrane, Mr. Edjericon, Hon. Julie Green, Mr. Jacobson, Mr. Johnson, Ms. Martselos, Ms. Nokleby, Mr. O'Reilly, Ms. Semmler, Hon. R.J. Simpson, Mr. Rocky Simpson, Hon. Shane Thompson, Hon. Caroline Wawzonek, Ms. Weyallon-Armstrong.
Topics
Statements

Minister’s Statement 270-19(2): Prohibition Creek Access Road Project Procurement Process and Project Update

Mr. Speaker, today I am providing an update on the Prohibition Creek Access Road Project to correct the public record, refute some misinformation, and also address some of the recent allegations raised in this House about the procurement process for this project.

First, the Prohibition Creek Access Road Project is, and always has been, advanced as a capacitybuilding project. The goal is to help prepare businesses, workers and residents to make the most of opportunities provided by the eventual construction of the entirety of Mackenzie Valley Highway.

Mr. Speaker, the Government of the Northwest Territories originally received federal funding to advance the design and construction of 13kilometres of allseason road from Canyon Creek to Prohibition Creek, which is near Norman Wells, in June 2020. That same month, the GNWT announced this project would be procured through a public tendering process, following the receipt of a regulatory approval, and completion of final design. In November 2020, the GNWT obtained approvals to advance the project. However, prior to initiating the procurement process, an environmental and engineering issue was identified at the Christina Creek Crossing, which is approximately halfway between Canyon Creek and Prohibition Creek, which would require additional design and regulatory work. In an effort to keep the project and capacitybuilding in the region moving forward, a decision was made to split the construction project into two phases.

Phase 1 construction included building 6.7kilometre allseason road between Canyon Creek and Christina Creek, and Phase 2, the construction would also include the remaining 6.3 kilometres from Christina Creek to Prohibition Creek.

The GNWT initiated a public procurement process for Phase 1 construction in October of 2021. The amount of time that lapsed between securing regulatory approval and initiating the procurement process was caused by the engineering challenges at Christina Creek and the change in project approach that I just described.

HRN Contracting Ltd. was the only business to submit a bid for Phase 1 construction through that public procurement process. Ultimately, the sole bid exceeded the available funding, and the procurement process was cancelled to reevaluate the project's budget and financing.

The Prohibition Creek Access Road Project is one of several infrastructure projects that have experienced cost escalations recently. Large and systemic cost increases associated with the COVID19 response, supply chain issues, inflation, material and labour shortages, and rising fuel prices have had an impact on project costs.

Following the cancellation of the public tender, the Department of Infrastructure engaged with Canada to revise the project delivery plan and very recently secured additional funding for Phase 1 construction, as well as design and engineering work required for the remainder of the 13kilometre road, including the Christina Creek Crossing.

Mr. Speaker, I can also confirm that a negotiated contract request from HRN Contracting Ltd. for Phase 1 construction was also received following the cancellation of the public tendering process. This request is currently being advanced as per the provisions in of the GNWT's Negotiated Contracts Policy. HRN Contracting Ltd. is a GNWT BusinessIncentivePolicy registered business in the Sahtu, owned by a Sahtu beneficiary and, as mentioned, was the sole bidder through this previous public procurement process.

Mr. Speaker, while it would be inappropriate for me to discuss the specifics of a contract on the floor of this House, I can assure you that it's our intent to advance this project to see the local and regional benefits maximized within the GNWT procurement and Negotiated Contract Policy, all of this to say, Mr. Speaker, this project has not been without its challenges. However, the allegations of nefarious dealings raised in the House are fundamentally untrue. It is our hope that procurement will be finalized in the near future, construction on this important capacity building project can begin this fall, and we are hopeful that this can be celebrated as the important milestone that it is, and that the years of work to get to this point are not tarnished by these recent allegations. Thank you, Mr. Speaker.

Speaker: MR. SPEAKER

Thank you, Minister. Ministers' statements. Minister responsible for Housing NWT.