Debates of October 6, 2023 (day 168)
Question 1638-19(2): Cameron HIlls Gas Field Remediation and Liabilities
Merci, Monsieur le President. You know that I couldn't squander this last opportunity to go back to my favorite Minister, the Minister of Environment and Climate Change, on one of my favourite topics, Cameron Hills remediation. So here goes, Mr. Speaker.
You know, so I want to ask about the last report I can find of anything happening at the Cameron Hills abandoned sour gas field is dated March 2023 when well remediation at about 44 sites was winding down. There has been no reports about the court from the courtappointed receiver now for ten months. I want to ask the Minister what's been going on at the site since March of this year. Mahsi, Mr. Speaker.
Thank you, Member for Frame Lake. Minister responsible for Environment and Climate Change.
Thank you, Mr. Speaker. I'm going to take 16 minutes and 5 seconds to answer this question. I guess I can't. Mr. Speaker, phase 1 of the environmental assessment site assessments were completed on 20 wells. Inspection of the sites were conducted by GNWT and OROGO. Most of the production and significant discovery licenses have been surrendered. Thank you, Mr. Speaker.
Okay. Merci, Monsieur le President. I want to thank the Minister for that. So we've had some inspections done. But it doesn't sound like much work is actually happening at the site. So, you know, given this lack of activities and reporting on the site over the last seven months, I'm hoping that the Minister can explain the schedule and remaining work to be done at Cameron Hills. Mahsi, Mr. Speaker.
Thank you, Mr. Speaker. Mr. Speaker, remaining work under OROGO order includes gas mitigation testing on 24 wells. Upon conclusion of the fire season, cut and cap four wells that require gas mitigation testing and removal of pipeline segment attached to two quad bridges, removal of bridges, a culvert, and main camp buildings.
All this may have been impacted by the fire over the summer. Removal of the intergovernmental or sorry, interprovincial pipelines. However, the Canadian energy regulator has does not want it removed yet. Conduct phase 2 environmental assessment site assessment and ground truth inventory environmental liabilities remain at the sites, such as contaminated soil, sumps, and site infrastructure. Thank you, Mr. Speaker.
Merci, Monsieur le President. I want to thank the Minister for that. Wow, that sounds like there's still a lot of work that needs to be done. It's going to cost a lot of money, and we want to make sure there's some local benefits there. But when I look at the public registry for the Mackenzie Valley Land and Water Board, there's still no submission of a final closure and reclamation plan or even a cost estimate of the environmental liabilities. So I'd like to know from the Minister when that plan and cost estimate will be submitted to the land and water board, and why it's been delayed for years. Mahsi, Mr. Speaker.
Thank you, Mr. Speaker. Mr. Speaker, Strategic Oil and Gas Limited has been under receivership since 2020, and the receiver is legally responsible for managing the site and all regulatory requirements. The receiver reports to the Alberta Court of King's Bench. The land and water board approved conceptional closure and reclamation plan in 2020. A revised closure and remediation plan with other work at the sites is required by June of 2024. Thank you, Mr. Speaker.
Thank you, Minister. Final supplementary. Member for Frame Lake.
Merci, Monsieur le President. Just one more question of for my favorite Minister, and I'm sending it with love, the site is located in the Northwest Territories but the first phase of the remediation work was awarded to an Alberta company with no local benefit requirements, even though some Indigenous governments wanted to do the work. So I'm going to ask the Minister if he can explain how GNWT is going to ensure local benefits moving forward, you know, we're trying to build a remediation economy, so how are we going to get local benefits from our remaining work? Mahsi, Mr. Speaker.
Thank you, Mr. Speaker. And I feel the love from the Member. I greatly appreciate it. And it's the last set of questions, so thank you very much.
On a serious side, Mr. Speaker, ECC is working with ITI and various levels of governments on building a remediation economy that includes capacity building for Indigenous businesses. Thank you, Mr. Speaker.
Thank you, Minister. Oral questions. Member for Yellowknife North