Question 86-16(1): Deh Cho Bridge Project Update

Thank you, Mr. Speaker. Mr. Speaker, the Deh Cho Bridge has been a topic of much debate the last few days and I believe the November 30th date was to be a very important and critical date. I would like to know if the Minister of Transportation could give us an update on the status of the Deh Cho Bridge project to find out where it sits. Thank you.

Speaker: MR. SPEAKER

Thank you, Mr. Hawkins. The honourable Minister of Transportation, Mr. Yakeleya.

Return To Question 86-16(1): Deh Cho Bridge Project Update

Thank you, Mr. Speaker. Mr. Speaker, this morning I was notified and am happy to report to the House that I heard from the president of the Deh Cho Bridge Corporation, Mr. Michael Vandell. We were advised the last couple of hours by Transport Canada that their navigable waters to construct the Deh Cho Bridge across the Mackenzie River was approved by the navigable waters protection office of Transport Canada. This is good news for the Northwest Territories. Now the corporation can close the financial arrangements under the public/private partnership and make preparations to begin construction on the long-awaited Deh Cho Bridge.

Speaker: MR. SPEAKER

Thank you, Mr. Yakeleya. Supplementary, Mr. Hawkins.

Supplementary To Question 86-16(1): Deh Cho Bridge Project Update

Thank you, Mr. Speaker. I have always, in principle, been a big supporter of the Deh Cho Bridge project. I think it’s a good project. Mr. Speaker, there were a lot of problems associated with this project and, as I understand it, there were still 12 outstanding issues. If the Minister is not prepared to give me an answer on every single one of those 12 issues that are still outstanding today, will he provide Members details on every one of those issues and how we are remedying them in the next few days? Can he provide that by the end of next week? Thank you.

Speaker: MR. SPEAKER

Thank you, Mr. Hawkins. Mr. Yakeleya.

Further Return To Question 86-16(1): Deh Cho Bridge Project Update

Thank you, Mr. Speaker. Mr. Speaker, I want to, first of all, congratulate the people of the aboriginal corporations in Fort Providence, the Metis, the band, the hamlet, the people in Fort Providence and the people of the Deh Cho, the Deh Cho Corporation also, and the GNWT department staff in terms of making an historical agreement that would see a project like this be very successful in the Northwest Territories. Once we have done our work in terms of working it out with the Deh Cho Bridge Corporation in terms of some of the 12 outstanding issues, we would certainly be happy to share that with the Members.

Speaker: MR. SPEAKER

Thank you, Mr. Yakeleya. Supplementary, Mr. Hawkins.

Supplementary To Question 86-16(1): Deh Cho Bridge Project Update

Thank you, Mr. Speaker. Mr. Speaker, the people concerned about the 12 outstanding issues I don’t think are in any way concerned about the bridge in principle. It is more about the nuts and bolts of this agreement to make sure it is online and on track. So, Mr. Speaker, I heard the willingness of the Minister to provide this. I just want to get some timelines on when we can actually see this document in front of us so we can really understand the fullness of what has been fully committed to this project. Thank you.

Speaker: MR. SPEAKER

Thank you, Mr. Hawkins. Mr. Yakeleya.

Further Return To Question 86-16(1): Deh Cho Bridge Project Update

Thank you, Mr. Speaker. Mr. Speaker, certainly, once we have arranged our discussions and some final discussions with the Deh Cho Bridge Corporation, our staff, this government on this side here, then we would produce the concession agreement for the Members here. I cannot say right now as to when those timelines would be stated as we still need to meet with the bridge corporation and work on some of those issues that would see a conclusion to this concession agreement.