Mr. Abernethy, Mr. Beaulieu, Ms. Bisaro, Mr. Bromley, Hon. Paul Delorey, Mrs. Groenewegen, Mr. Hawkins, Mr. Jacobson, Mr. Krutko, Hon. Jackson Lafferty, Hon. Sandy Lee, Hon. Bob McLeod, Hon. Michael McLeod, Hon. Robert McLeod, Mr. Menicoche, Hon. Michael Miltenberger, Mr. Ramsay, Hon. Floyd Roland, Mr. Yakeleya
Topics
Statements

QUESTION 73-16(4): CHIPSEALING THE DEH CHO TRAIL

Thank you, Mr. Speaker. My questions are for the Minister of Transportation and a follow-up on my Member’s statement. I know that this year we were supposed to have I think it was 70 kilometres of chipseal done from the Providence junction towards Fort Simpson. I know that it was issued later in the year. I just want to ask the Minister again, what are the current plans the department has to complete this work and how soon? Thank you.

Speaker: MR. SPEAKER

Thank you, Mr. Menicoche. The honourable Minister of Transportation, Mr. Michael McLeod.

Thank you, Mr. Speaker. I’d have to go to the department and confirm, but I believe the project has been deferred until next year. There was some concern, as the season progressed, with the amount of rain that we got and the saturation that the road became. Mr. Speaker, it’s something that we’d still like to move forward on. There were questions raised by the Member on some of the other projects in his riding, including Highway No. 7 that we had to defer. It’s really unfortunate; however, we can’t control the weather, and we’ll commit to having those projects moved forward as soon as possible in the new year.

Certainly the residents of my riding were quite excited to have this project completed this year. However, we’re patient people and we’re glad to see that chipseal is coming, Mr. Speaker. I’d just like to know the department’s plans of any further work on chipsealing Highway No. 1 towards Fort Simpson beyond this in the new fiscal year 2010. Thank you.

Mr. Speaker, we’ve got a fairly aggressive plan to work on Highway No. 1 and other projects in the Member’s riding, including Highway No. 7. We certainly have heard the comments he made in his Member’s statement on a number of occasions and we’ve put together a budget over the next four years where we’ll be targeting roughly $30 million to...All the portions that require reconstruction, that Highway No. 1, needs to be widened from the border to Enterprise. We’re also looking at doing some reconstruction from the junction of Highway No. 3 towards Simpson and, of course, Highway No. 7 needs fairly significant investment in terms of upgrades. The road has been really deteriorating and it’s an aging piece of infrastructure with very poor soil conditions. We’re going to try to get that all fixed up as soon as we can. Thank you.

I’m pleased that certainly the department is making great strides and hopefully we can accomplish a lot of this work in 2010. In terms of Highway No. 7, Fort Liard residents have seen the B.C. side. They actually chipsealed their road up to the B.C. border, and they’re asking me continuously when are we going to re-chipseal the road from Fort Liard back to the B.C. border once again. They’re also looking to see the completion of the reconstruction that’s occurring there. Thank you.

Mr. Speaker, that’s a difficult question to answer at this point. We are still doing a lot of work on the Highway No. 7 section, including an engineering assessment and functional design. We’re also doing some of the necessary material preparation, crushing of the kilometre 3 and doing some of the upgrades that are required.

As to doing some actual chipseal, maybe. It’s not something that we’ve decided as of yet. It’s something that we’d like to do. Chipseal, of course, is something that really is dependent on the base and we’d have to be convinced that the road is going to hold up. It will be a decision that we will consider, but it’s not a decision we have made as of today. Thank you.

Speaker: MR. SPEAKER

Thank you, Mr. McLeod. Final supplementary, Mr. Menicoche.

Thank you very much, Mr. Speaker. Is the Minister of Transportation prepared to see that the chipseal will return to the residents of Fort Liard as they travel to B.C.? Thank you.

Mr. Speaker, it’s our goal to see chipseal applied to most of our roads, if not all of them, for the long term. As of yet, we haven’t been able to really prove that it will stay in sandy conditions such as the Fort Liard area. We know some work was done on the B.C. side. We’re going to take a look at that and see if we can do some test areas over the next while. We’d also like to do chipsealing on Highway No. 8 and other highways, for example. We think it’s going to solve some of our safety issues and reduce some of the maintenance required, but we still have to ensure that it’s going to work and we have to make sure we have our technology all figured out before we do that. But that’s our goal.

We’re also, Mr. Speaker, trying out different products that we think may be more durable than chipseal. Of course, any time you start moving that area, the costs go up. There’s still a lot of work and a lot of research that we need to do, but that’s our intentions. Thank you.

Speaker: MR. SPEAKER

Thank you, Mr. McLeod. The honourable Member for Frame Lake, Ms. Bisaro.