Debates of October 22, 2020 (day 42)

Date
October
22
2020
Session
19th Assembly, 2nd Session
Day
42
Members Present
Hon. Diane Archie, Hon. Frederick Blake Jr., Mr. Bonnetrouge, Hon. Paulie Chinna, Ms. Cleveland, Hon. Caroline Cochrane, Hon. Julie Green, Mr. Jacobson, Mr. Johnson, Mr. Lafferty, Ms. Martselos, Ms. Nokleby, Mr. Norn, Mr. O'Reilly, Ms. Semmler, Hon. R.J. Simpson, Mr. Rocky Simpson, Hon. Shane Thompson, Hon. Caroline Wawzonek
Topics
Statements

Question 397-19(2): Inuvik Airport

Thank you, Mr. Speaker. Can the Minister of Infrastructure provide me with a list of all the projects that are planned for the Inuvik airport and runway extension? Thank you, Mr. Speaker.

Speaker: MR. SPEAKER

Thank you, Member for Inuvik Twin Lakes. Minister of Infrastructure.

Thank you, Mr. Speaker. There are three capital projects that are planned for the Inuvik Mike Zubko Airport. The first one is a new air terminal building, which will replace the current air terminal building. The second project we have is the airport civil improvements, and this is to bolster the airport's resilience towards climate change. Finally, we have the runway extension that is meant to increase the runway length by about 3,000 feet. Thank you, Mr. Speaker.

Can the Minister tell me what work has already been awarded out of those?

The design of the new air terminal building has been awarded, and it has been awarded to Stantec. That was done through an RFP, the request for proposal. Also, the demolition of the RCMP hangar was awarded to Delta Northern Alliance of Inuvik, and that was done through negotiated contract. Delta Northern Alliance is an Inuvialuit and Gwich'in business entity. Finally, the design of the airport civil improvements and the runway extension was awarded to Associated Engineering, and that also was done through a request for proposal.

Can the Minister tell me what work has yet to be put out, then, to be awarded and how we are ensuring that northern businesses are getting all this work?

Mr. Speaker, the department has been authorized to pursue a negotiated contract, and that is with the Delta Northern Alliance, the DNA, for the construction of the new airport terminal. The department will be providing the completed design documents to DNA in early 2021, so that is just after the new year, to begin the negotiated contract process. The runway extension is a 100-percent federally funded project. Having said that, the GNWT must abide by the requirements to ensure that contracts are awarded and managed in accordance with the federal policies and their procedures.

Speaker: MR. SPEAKER

Thank you, Minister. Oral questions. Member for Inuvik Twin Lakes.

Thank you, Mr. Speaker. My final question to the Minister is: does the Minister have a timeline of when the work that is yet to be done to start, and how long does the department figure that it's going to take until it's completed? Thank you, Mr. Speaker.

If it were up to me, it would be started yesterday, as the Member for Inuvik Twin Lakes will know. However, in the worst-case scenario, we anticipate the air terminal building construction to begin in the fall of 2021 and to be completed by 2023-2024. We also anticipate the pre-construction work, which it's called the granular production, for the civil improvements to begin as early as February 2021 and the construction expected to be completed by 2022. Currently, there is no funding agreement in place for the construction of the runway extension. However, the Department of Infrastructure is anticipating discussions with the department of defence by November 2021. Thank you, Mr. Speaker.

Speaker: MR. SPEAKER

Thank you, Minister. Oral questions. Member for Nunakput.