Debates of February 5, 2025 (day 38)
Question 435-20(1): Aspen Building Project Update

Thank you, Mr. Speaker. Because I like asking questions to the Minister of housing, I think I'm going to ask another one.
It's been taking a long time, glacial pace, to get the Aspen Building project up and running. My understanding is the doors were just kicked open the other day, and the contractors start -- finally started work on that. Can the Minister start off our discussion today with what's actually happening and when's that project anticipated to be completed. Thank you.
Thank you, Member for Yellowknife Centre. Minister responsible for Housing NWT.

Well, good news. The contract has been awarded, as the Member knows, and we're hoping to have completion fall of 2025. Thank you, Mr. Speaker.

Mr. Speaker, we all know housing opportunities don't runneth over. So in other words, there's not an oversupply in housing opportunities certainly here in the capital or even in the regions and small communities. Mr. Speaker, what was the delay specifically as to get this initiative off the ground and into the construction phase? Because the last major report we had on this was through the Premier's office where they were trying to evict the squatting tenants, as they say, so they could start construction. So can we find out what the delay was. Thank you.

Mr. Speaker, with Housing NWT and our contracting process, we have to run through a number of processes and making sure that we're following policies with Housing NWT, including the delay with the encampment, securing the site, and ensuring the employees on site are safe and secure. So thank you, Mr. Speaker.
Minister responsible for Housing NWT. Final supplementary. Member from Yellowknife Centre.

Thank you, Mr. Speaker. I'm glad to hear the Minister's now converting to the Minister of process because it seems to come out on almost every answer that the process will be led by the process once we're convened on the process.
Mr. Speaker, can the Minister be more specific because the encampment was removed, in large part, out of the way months ago. Furthermore, I think there with a lone holdout still wouldn't have caused an issue. That said, there must have been a real reason that contract had not started. And I'm asking what's the delay because ultimately, Mr. Speaker, I want to know who is responsible for the delay. Was it the contractor? Was it the GNWT? And will we be taking responsibility? I think the Premier's waving at you, Mr. Speaker. Thank you.

Thank you, Mr. Speaker. I'm a little distracted here as well. But, yes, there's processes. If I'm the Minister of processes, that's fine. But, again, we have to follow process. We are government. We're a public government. So, again, Aspen Apartments, it's gone through a number of things. We have awarded a contract. The work is ongoing. The site is secure. There was an encampment issue. There's a number of things that happened. So thank you, Mr. Speaker.