Debates of May 31, 2016 (day 11)

Topics
Statements

Question 125-18(2): Delayed Spring Ferry Service in Mackenzie Delta

Thank you, Mr. Speaker. Mr. Speaker, I have questions for the Minister of Transportation. Mr. Speaker, since April many scientists predicted an early spring and also a number of elders, so we've had a lot of time to prepare for an early spring. With the early spring we’ve had why did the service begin this past Sunday afternoon in Tsiigehtchic and not any sooner? Thank you, Mr. Speaker.

Speaker: MR. SPEAKER

Masi. Minister of Transportation.

Mr. Speaker, the Member is correct. We did experience an earlier spring than normal. As the river broke up early on the Peel and the Mackenzie it kind of caught the department a little off guard in getting some of these things. One of the issues with the Tsiigehtchic and Peel River ferries was we had scheduled Transport Canada inspectors to come in for the replacement bottom of the Tsiigehtchic ferry, and at the same time they're in there to do the Peel River ferry. With the early spring and stuff, it's kind of caught us off guard from our normal scheduling, so that's one of the reasons for the holdup was the late arrival of federal inspectors.

Mr. Speaker, as I mentioned, the Tsiigehtchic ferry was launched on Friday I believe and started service Sunday afternoon. I'd like to ask the Minister: why is the Peel River ferry not launched and not in service at this time?

As I alluded to earlier in my statement that the transportation of Canada inspector was in. He was there to look at the Tsiigehtchic ferry as we replaced the bottom of that ferry and put it in and do its seaworthiness which takes a couple days of trials and stuff. When they were finished that they moved on to the Peel ferry. The Peel ferry is in the process of going through its inspection as such and with the low water now expected after high water from breakup we now have five anchor points available to run this ferry. The original anchor points that showed up after breakup, there were only two and that's not significant enough to have the ferry run safely for the general public.

Mr. Speaker, the Minister just mentioned that the water level is too high at this time. I'm not sure who the Minister is getting his information from because I get this from the people that live in Fort McPherson that have traditional knowledge in that area. There's nothing wrong with the water level right now. Right now the landing should be in and you know if the inspections are complete there's no reason why the ferry is not in. I'd like to ask the Minister, when will the service begin on the Peel River ferry?

As I alluded, there's five anchor points now available and as of today the slipways are being prepped and the timbers are being installed to launch the ferry. As of this evening, we plan on having the ferry into the Peel system and with more seaworthiness testing we're hoping to have the ferry service in operation by late Wednesday, early Thursday morning.

Speaker: MR. SPEAKER