Debates of June 7, 2012 (day 11)

Topics
Statements

QUESTION 99-17(3): DEH CHO BRIDGE PROJECT COST OVERRUNS

Thank you, Mr. Speaker. My residents are concerned about the construction of the Deh Cho Bridge as well. I would like to ask the Minister of Transportation some questions. I think the concern is that it was really no great surprise that the cost continues to rise and they continue to come to this House for expenditures. Can the Minister assure this House that once this final deal is done, the bleeding will stop, so to speak?

Speaker: MR. SPEAKER

Thank you, Mr. Menicoche. The honourable Minister of Transportation, Mr. Ramsay.

Thank you, Mr. Speaker. All expectations are that this will be the final ask. It’s going to allow us to have the bridge open this fall. We have also negotiated an end to the claims back and forth on the construction of the project. This is going to be something that we continue to pursue until the bridge is complete in November. Thank you.

Mr. Speaker, I can appreciate some of the past issues that the Auditor General’s report spoke of incomplete designs, et cetera. Is the Minister confident in telling this House that all considerations and risk factors have been taken into account to date and that they can achieve this November 2012 opening, especially with this new deal that he is talking about with the contractor? Thank you.

Mr. Speaker, I thank the Member for the question. Again, it’s our expectation that the bridge will be open in November. We were weighing a few different options in how we could look at this. This was the option that would allow us to get budget certainty and also schedule certainty that would enable us to move forward and complete this project by November.

Again, it wasn’t easily arrived at. We have been in negotiations for a number of weeks with the contractor. This is our best effort to move this project along and get the project complete. Thank you.

Mr. Speaker, I guess I’m trying to get at the point that in the past there were unforeseen and incomplete things being done. Can the Minister assure us that all aspects of bridge construction have been considered and that this side of the House and the general public have no reason to expect further delays or further cash output from our government and hence the taxpayers of the Northwest Territories? Thank you.

Mr. Speaker, there always could be potentially unforeseen circumstances, but again, my expectation – and I have been following this project closely for a number of years – is that this will be the final ask of this government to see the completion of the Deh Cho Bridge in November of this year. We can move on after that. Thank you.

Speaker: MR. SPEAKER

Thank you, Mr. Ramsay. Final, short supplementary, Mr. Menicoche.

Thank you, Mr. Speaker. All things being considered, I know that last year we had shipping delays, production delays. Is there any of that on the table? What does this House have to expect, or have all things been considered? Thank you.

Mr. Speaker, pertaining to the completion of the construction of the Deh Cho Bridge, this is all encompassed in the negotiated deal that we have with the contractor to complete the project. It is in there. This is our way forward so that we can see the bridge get completed this fall so we can get budget certainty and we can get schedule certainty. Thank you.

Speaker: MR. SPEAKER

Thank you, Mr. Ramsay. The honourable Member for Yellowknife Centre, Mr. Hawkins.