Hon. Diane Archie, Hon. Frederick Blake Jr., Mr. Bonnetrouge, Hon. Paulie Chinna, Ms. Cleveland, Hon. Caroline Cochrane, Hon. Julie Green, Mr. Jacobson, Mr. Johnson, Mr. Lafferty, Ms. Martselos, Ms. Nokleby, Mr. Norn, Mr. O'Reilly, Hon. R.J. Simpson, Mr. Rocky Simpson, Hon. Shane Thompson, Hon. Caroline Wawzonek
Topics
Statements

Return to Written Question 23-19(2): Practice of Using Power-Limiting Devices in the Northwest Territories

Speaker: Mr. Rutland

Thank you, Mr. Speaker. I have a return to written question 23-19(2) asked by the Member for Nunakput on March 4, 2021, regarding the practice of using power-limiting devices in the Northwest Territories.

The data for the Northwest Territories Power Corporation was compiled at 12:00 noon on March 5th. The numbers fluctuate on a regular basis due to the timing of Northwest Territories Power Corporation's billing cycles. The Northwest Territories Power Corporation had 72 residential load limiters in place. There had been a total of 336 load limiter instances since collection activities resumed on November 9, 2020. These instances could be multiple occurrences on a single location and does not represent 336 unique customers.

For the Northland Utilities Ltd. Limiters, a breakdown of the number of load limiters per community for both Northland Utility companies as of the week of March 15, 2021, is as follows:

Northland Utilities Ltd. (Yellowknife):

Yellowknife - two load limiters

Northland Utilities (NWT):

Hay River - four load limiters

Hay River Reserve - two load limiters

Enterprise - one load limiter

Fort Providence - one load limiter

Trout Lake - four load limiters

Thank you, Mr. Speaker.